E&E Assembly in Johor: Environmental, Effluent & Power Compliance Guide
A regulatory entry guide for electronics & electrical (E&E) assembly plants in Johor Bahru — EIA classification, industrial effluent (Standard A / B) limits, scheduled-waste handling, and TNB power-connection thresholds, with official statutory sources.
Site Positioning & Supply Chain
Electronics & electrical (E&E) assembly clusters mainly in Tebrau and Senai — eastern Johor Bahru’s most active industrial belts. Tebrau adjoins the Eastern Dispersal Link (EDL), roughly 15 minutes from the Causeway, with a ready labour pool from Setia Tropika and Bandar Dato Onn, and sits inside the JS-SEZ Flagship Zone B incentive perimeter. Core activities include printed-circuit-board assembly (PCBA), component soldering and consumer-electronics final assembly; the compliance focus is power-quality sensitivity plus trace soldering effluent and specific scheduled-waste streams.
Environmental Impact Assessment (EIA)
Under section 34A of the Environmental Quality Act 1974 (Act 127) and the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015, a light E&E assembly and test plant typically falls under the First Schedule. The project proponent appoints a DOE-registered environmental consultant to prepare the EIA report and submits it to the Johor State DOE office for review and approval. First Schedule activities are generally exempt from mandatory public display, so the approval pathway is comparatively efficient.
Industrial Effluent (IETS) Compliance
Board cleaning, mould maintenance and cooling generate industrial effluent governed by the Environmental Quality (Industrial Effluent) Regulations 2009 [P.U.(A) 434/2009]. Before construction or modification works that create a new discharge source, the occupier must give the Director General prior written notification under regulation 4. Standard A applies where the discharge point lies upstream of a gazetted water catchment (e.g. the Johor River); Standard B applies otherwise. The plant must operate a compliant industrial effluent treatment system (IETS) supervised by a DOE-certified competent person.
| Parameter | Standard A | Standard B |
|---|---|---|
| Temperature | 40 °C | 40 °C |
| pH value | 6.0 – 9.0 | 5.5 – 9.0 |
| BOD₅ (5 days, 20 °C) | 20 mg/L | 50 mg/L |
| Suspended Solids | 50 mg/L | 100 mg/L |
| Lead (Pb) | 0.10 mg/L | 0.5 mg/L |
| Copper (Cu) | 0.20 mg/L | 1.0 mg/L |
Fifth Schedule, Environmental Quality (Industrial Effluent) Regulations 2009 [P.U.(A) 434/2009].
Scheduled Wastes Handling
Waste printed circuit boards, solder-paste residues and component-cleaning solvents are scheduled wastes regulated by the Environmental Quality (Scheduled Wastes) Regulations 2005 [P.U.(A) 294/2005]. On-site storage is limited to 180 days or less, and accumulation must not exceed 20 metric tonnes without prior written DOE approval. Containers must be labelled with the generation date, waste code and generator contact; transfers run through the DOE electronic consignment (e-Consignment) system to licensed recovery or treatment facilities.
| SW Code | Waste Type | Compliance Action |
|---|---|---|
| SW 110 | Waste electronic assemblies / PCBs containing lead, antimony, cadmium | Time-limited storage, labelling, e-Consignment declaration, licensed recovery |
| SW 322 | Spent organic cleaning solvents (e.g. isopropyl alcohol, IPA) | Explosion-proof store, secondary containment bund, time-limited removal |
Environmental Quality (Scheduled Wastes) Regulations 2005 [P.U.(A) 294/2005], First Schedule.
Power Demand & TNB Connection
E&E equipment is sensitive to voltage sag, so siting requires an early Maximum Demand (MD) consultation with TNB. A single-line diagram (SLD) signed by a registered Professional Engineer (PE) is submitted to the Energy Commission (Suruhanjaya Tenaga, ST) under the Electricity Supply Act 1990 (Act 447). For applications submitted after 22 November 2024, TNB bears the substation plinth construction and equipment cost where the developer hands over setback-compliant substation land.
| MD Range | Substation Requirement | Footprint |
|---|---|---|
| Below 350 kVA | Supply via existing low-voltage network; system capacity assessment | Metering room only |
| 350 – below 1000 kVA | 11/0.4 kV compact substation (CSU); PBT setback applies | 5 m × 7 m |
| 1000 – below 5000 kVA | 11/0.4 kV or 11 kV PE distribution substation | Per TNB ESAH |
TNB Electricity Supply Application Handbook (ESAH); Electricity Supply Act 1990 (Act 447).
Frequently Asked
Which effluent standard applies to an E&E plant in Tebrau?
Standard A applies if the discharge point lies upstream of a gazetted water catchment (e.g. the Johor River); otherwise Standard B. Key Fifth Schedule limits are BOD₅ 20/50, Suspended Solids 50/100, Lead 0.10/0.5 and Copper 0.20/1.0 mg/L (Standard A / B).
Does an E&E assembly project need an EIA?
Light E&E assembly and test typically falls under the First Schedule of the EIA Order 2015. A DOE-registered consultant prepares the EIA report for the Johor State DOE; First Schedule activities are generally exempt from mandatory public display.
Which scheduled-waste code covers waste printed circuit boards?
SW 110 covers waste electronic assemblies and PCBs containing lead, antimony or cadmium; spent cleaning solvents such as IPA fall under SW 322. On-site storage is capped at 180 days and 20 metric tonnes without prior DOE approval.
At what power demand does an E&E plant need its own substation?
Below 350 kVA usually connects via the existing low-voltage network; 350–1000 kVA requires an 11/0.4 kV compact substation (CSU, about 5 m × 7 m); 1000–5000 kVA requires a PE distribution substation. The single-line diagram must be signed by a registered PE and submitted to the Energy Commission (ST) under the Electricity Supply Act 1990 (Act 447).
References
Looking for property in Johor?
Browse live listings, or explore by area — and for siting advice or negotiation, talk to our industrial property specialist, Grace.
Related Guides
Source
Original content by JB Factory · © 2026 JB Factory. When citing or reproducing, please attribute the source and keep the original link: https://jbfactory.com.my/en/wiki/electronics-electrical-assembly
Specialist behind this guide: Grace Yan — Industrial Property SPECIALIST (REN 18395). WhatsApp / Tel +60 16-746 9998 · WeChat IndLand_GraceYan
Disclaimer
This guide is general information only. It is not legal, tax, or investment advice, and is not an offer or solicitation. The laws, rates, thresholds, and policies referred to may change at any time. Always confirm the current position with the relevant authority and seek qualified professional advice before acting.